Apartment make-ready checklist and turn timeline

An apartment make-ready checklist in the order the work happens, with tick boxes by area, a vendor line for each, and a turn timeline: the target ready date, the earliest sensible showing date if you market during the make-ready, and the vacant days this turn will cost.

Set the move-out date, the unit type and the scope, then adjust the days for each area to match your trades. Repairs by area run alongside each other; paint, flooring, the final clean and the ready inspection follow in that order, so no trade undoes another's work. Changing the unit type or scope resets the days.

Every day count here is a placeholder, not a benchmark. We know of no published US or Canadian series for make-ready time; replace them with your own after a quarter of measuring.

This turn

Your estimate. 0 if the next lease is signed before the unit is ready; longer if marketing waits for ready.

Turn timeline

Target ready date — a turn of — after move-out

Earliest showing, if you market during make-ready — once paint and flooring are done

Vacant days this turn — turn length + days to lease start

When each phase finishes
Repairs finish (the longest area)—
Paint finishes—
Flooring finishes—
Final clean finishes—
Ready inspection: unit available—

Price these vacant days in the vacancy cost calculator, or add them to your unit-days in the vacancy rate calculator.

Before move-out

Day −10

  • About ten days before move-out: walk every room with the move-in condition report
  • Photograph anything that will need a trade
  • Set the scope (light, standard or heavy) and book the trades for dates after move-out
  • Order parts with lead times: appliance parts, blinds, fixtures
  • Give the tenant a written move-out checklist

Move-out day: inspection, keys and locks

Day 0

  • Keys back; re-inspect against the pre-move-out notes, with photos
  • Locks changed or re-keyed; keys, fobs and mailbox key labelled and logged
  • Meter readings recorded; utilities moved to the firm's name
  • Damage beyond normal wear documented for the deposit process, on the timeline your jurisdiction sets

Entry, doors and security

Repairs: run alongside the other areas

  • Doors close, latch and lock; entry door and viewer intact
  • Windows open, close and lock; screens present
  • Smoke and carbon monoxide alarms tested and dated, as local rules require

Kitchen

Repairs: run alongside the other areas

  • Fridge cold, oven and burners heat, dishwasher runs a full cycle, hood fan and light work
  • Sink drains, no leak underneath, faucet and sprayer work
  • Counters and backsplash undamaged and caulked; cabinet doors and drawers close

Bathrooms

Repairs: run alongside the other areas

  • Toilet flushes and refills without running; seat secure
  • Tub or shower drains; caulk fresh; no mildew
  • Exhaust fan works; mirror, towel bars and fixtures secure

Heating, cooling and water

Repairs: run alongside the other areas

  • Heating and cooling run; filter replaced
  • Water heater set and not leaking
  • Thermostat works and is set for an empty unit

Living areas and bedrooms

Repairs: run alongside the other areas

  • Wall damage patched: holes, scuffs, tape marks
  • Outlets and switches work; cover plates on
  • Light fixtures work, bulbs matched; blinds intact and operating
  • Closet doors on their tracks

Paint

After every patch, before the floors

  • Walls and ceilings painted or touched up
  • Trim and doors touched up
  • Older building: the lead-paint rules that apply checked before any sanding or scraping

Flooring

After paint, so drips land on the old floor

  • Carpet cleaned, patched or replaced
  • Hard floors cleaned or refinished; transitions secure

Final clean

Last trade in, always

  • Top to bottom, after the last trade has left
  • Inside the fridge, oven, microwave and cabinets
  • Windows, sills and tracks; bathrooms

Ready inspection and photos

The unit is ready at the end of this

  • Inspected by someone other than the technician, against your written ready standard
  • Exceptions recorded and approved
  • Photos taken for the listing and the move-in condition report

Ready signed off by:

How the timeline is worked out

  • Day 0 is move-out: inspection, keys, locks and meters.
  • Repairs by area run at the same time, so the repair phase is as long as the longest area, not the sum of them.
  • Then in order: paint, flooring, final clean, ready inspection. The target ready date is move-out plus repairs plus each of those.
  • Earliest showing is the day after paint and flooring finish, when the unit reads as nearly finished. A unit with the carpet up shows like a building site; whether to show it at all before it is ready is a per-unit call.
  • Vacant days this turn = the turn length + your estimate of days from ready to lease start. Marketing from notice, rather than from ready, is what brings that second number down.

Placeholder days: a light turn comes to three days, a standard one-bedroom to five and a heavy one to ten; three or more bedrooms, or a house, adds a day to paint and flooring on standard and heavy turns, and a house adds a day of cleaning. Write your own in and the dates follow.

Releaser is available to property management firms in the United States and Canada. Each property becomes one shareable link: applicants answer your questions, you review who matches your criteria, and the ones you approve book a showing on your calendar.

Get early access

Get the updates by email.

One short note when something ships. No newsletters about newsletters.