Apartment make-ready checklist and turn timeline

A printable apartment make-ready checklist of 112 items in work order, with a turn timeline and ticks saved per unit.

This turn

Your estimate. 0 if the next lease is signed before the unit is ready.

Turn timeline

Target ready date — a turn of — after move-out

Earliest showing, if you market during make-ready — once paint and flooring are done

Vacant days this turn — turn length + days to lease start

When each phase finishes
Repairs finish (the longest area)—
Paint finishes—
Flooring finishes—
Final clean finishes—
Ready inspection: unit available—

Price these vacant days in the vacancy cost calculator, or add them to your unit-days in the vacancy rate calculator.

Before move-out

Day −10

  • About ten days before move-out: walk every room with the move-in condition report
  • Photograph anything that will need a trade
  • Set the scope (light, standard or heavy) and book the trades for dates after move-out
  • Order parts with lead times: appliance parts, blinds, fixtures, flooring
  • Give the tenant a written move-out checklist and where to return keys
  • Book the move-out inspection and the utility transfer for move-out day

Move-out day: inspection, keys and locks

Day 0

  • Keys, fobs, remotes and mailbox key returned and counted
  • Re-inspect against the pre-move-out notes and the move-in report, with dated photos
  • Damage beyond normal wear documented for the deposit process, on the timeline your jurisdiction sets
  • Meter readings recorded; utilities moved to the firm's name
  • Locks changed or re-keyed; keys, fobs and mailbox key labelled and logged
  • Anything left behind handled under your local rules on abandoned property
  • Pest check: droppings, egg cases, bed bug signs; treatment booked before paint if found
  • Water shut-offs and the breaker panel located

Repairs: the next 9 sections run at the same time, by different trades.

Life safety

  • Smoke alarms in every required location tested and dated; batteries replaced
  • Carbon monoxide alarms tested and dated, wherever there is fuel-burning equipment or an attached garage
  • Fire extinguisher present, charged and in date, where one is provided
  • Bedroom windows open fully for an emergency exit; any security bars release from inside
  • Stair and balcony railings and handrails secure
  • Blind and curtain cords out of a child's reach, or cordless coverings fitted
  • Notices your jurisdiction requires (exit routes, emergency numbers) posted

Doors, windows and locks

  • Entry door closes, latches and seals; deadbolt throws fully; viewer intact
  • Interior doors swing and latch without rubbing; door stops in place
  • Closet and bifold doors on their tracks
  • Sliding door glides and locks, with a security bar; screen door works
  • Windows open, close and lock; sashes stay up; no cracked or fogged panes
  • Screens present and untorn
  • Weatherstripping and door sweeps intact: no daylight around exterior doors
  • Hinges, handles and strike plates tight

Walls, ceilings and window coverings

  • Holes, dents, scuffs and anchor holes patched and sanded
  • Stains or mould on walls and ceilings traced to the source and fixed, not painted over
  • Baseboards, trim and door casings secure; gaps caulked
  • Blinds or other window coverings intact and working in every room, matched per room
  • Closet rods, shelves and hooks secure

Plumbing

  • Every faucet runs hot and cold without dripping; aerators clean
  • Every drain runs freely; stoppers work
  • No leaks under sinks; shut-off valves turn and supply lines are dry
  • Toilets flush and refill without running; seat tight; no rocking at the base
  • Tub and shower valve, diverter and head work; caulk and grout renewed
  • Water heater not leaking, relief-valve pipe in place, set no higher than 120°F (49°C)
  • Garbage disposal runs without leaking or jamming
  • Laundry hookups: valves turn, worn hoses replaced, drain clear
  • Water pressure checked at the fixture farthest from the supply

Electrical and lighting

  • Every outlet works; GFCI outlets by water and outdoors trip and reset
  • Every switch works; cover plates on, uncracked and matched
  • Light fixtures work; bulbs one colour temperature per room
  • Ceiling fans run at each speed without wobbling
  • Entry, patio and exterior lights work
  • Doorbell, intercom or buzzer works and shows the right unit
  • Breaker panel labelled; no tripped or warm breakers

Appliances

  • Fridge holds 37–40°F (3–4°C), freezer freezes; door seals close; shelves and bins complete
  • Ice maker and water dispenser work, or are shut off and labelled
  • Every burner lights or heats; oven bakes and broils to temperature; knobs complete
  • Range anti-tip bracket in place
  • Dishwasher runs a full cycle and drains; racks and spray arms intact
  • Microwave heats; turntable and light work
  • Hood fan and light work; grease filter cleaned or replaced
  • Washer and dryer run a full cycle; dryer vent cleaned and connected
  • Make, model and serial number of each appliance recorded

Heating, cooling and ventilation

  • Heating runs and reaches the set temperature
  • Cooling runs and reaches the set temperature; condensate drains
  • Filter replaced; size and date written in the unit log
  • Thermostat works, has fresh batteries and is set for an empty unit
  • Vents and return grilles cleaned; registers open
  • Bathroom and kitchen exhaust fans pull air
  • Outdoor or through-wall unit clear of debris

Cabinets, counters and bath fittings

  • Cabinet doors and drawers open, close and line up; hinges and pulls tight
  • Cabinet interiors undamaged; old shelf liner removed
  • Counters and backsplash undamaged; caulk renewed at sinks and walls
  • Vanity, mirror and medicine cabinet secure and unbroken
  • Towel bars, toilet-paper holder, shower rod and hooks secure
  • Shower doors and tracks clean and sealing

Balcony, storage and entry

  • Balcony or patio clear; floor drain open
  • Storage unit emptied; its lock removed or changed
  • Mailbox shows the unit only, with no previous tenant's name
  • Parking space, permit or garage remote reassigned
  • Unit number visible from the hallway or street

Paint

After every patch, before the floors

  • Older building (built before 1978 in the US): the lead-paint rules that apply checked before any sanding or scraping
  • Cover plates, alarms and fixtures removed or masked
  • Walls painted or touched up in one colour and sheen, recorded in the unit log
  • Ceilings painted where stained or patched
  • Trim, doors and frames touched up, closets included
  • Touch-ups checked in daylight once dry; plates and fixtures back on

Flooring

After paint, so drips land on the old floor

  • Carpet cleaned, re-stretched or patched; replaced if worn through or stained
  • Carpet pad dry, with no odour
  • Hard floors cleaned or refinished; damaged planks or tiles replaced
  • Vinyl and laminate seams tight; no lifting edges
  • Tile grout cleaned and sealed
  • Thresholds and transition strips secure

Final clean

Last trade in, always

  • Top to bottom, after the last trade has left
  • Fans, fixtures, vents and the tops of doors and cabinets dusted
  • Walls, switch plates and door handles wiped
  • Inside the fridge, freezer, oven, microwave and dishwasher
  • Inside every cabinet, drawer and closet
  • Range hood and filter degreased
  • Sinks, tubs, showers and toilets scrubbed; mineral deposits removed
  • Mirrors and glass streak-free
  • Windows, sills and tracks, sliding-door track included
  • Floors vacuumed and mopped, edges and corners included
  • Paint cans, offcuts and trash out of the unit

Ready inspection and photos

The unit is ready at the end of this

  • Inspected by someone other than the technician, against your written ready standard
  • Every light, appliance, faucet and lock operated once more
  • Exceptions recorded and approved, each with a date to fix
  • Keys, meter readings and appliance details matched to the unit log
  • Dated photos of every room and appliance for the move-in condition report

Listing and showing ready

Same day as the ready inspection

  • Listing photos taken in daylight: lights on, blinds level, nothing on the floors
  • Listing updated: rent, available date, fees, pet terms, floor plan
  • Unit marked ready in your system, with the available date
  • Showing access set: lockbox or smart-lock code, or key sign-out
  • Power on and thermostat set for showings
  • Move-in packet ready: keys, utility contacts, trash and recycling days
  • Last walk before the first showing: smells, dust, insects

Ready signed off by:

How the timeline is worked out

Set the move-out date, unit type and scope, then adjust each section's days to your trades (changing type or scope resets them). Every day count here is a placeholder, not a benchmark. We know of no published US or Canadian series for make-ready time; replace them with your own after a quarter of measuring.

  • Day 0 is move-out: inspection, keys, locks and meters.
  • Repairs by trade run at the same time: the phase is as long as the longest one, not the sum.
  • Then in order: paint, flooring, final clean, ready inspection, so no trade undoes another's work.
  • Earliest showing is the day after paint and flooring finish.
  • Vacant days = the turn + your days from ready to lease start. Marketing from notice, not from ready, brings the second number down.

Placeholders: light 3 days, standard one-bedroom 5, heavy 10; three or more bedrooms or a house adds a day to paint and flooring (standard and heavy), and a house a day of cleaning. Ticks, names and days stay in this browser, per property and unit; nothing is sent anywhere.

Common questions

What is an apartment make-ready checklist?

Everything a vacant unit needs between one lease and the next, in order: keys and inspection, repairs by trade, paint, flooring, the final clean, a ready inspection and photos.

How long should a make-ready take?

There is no published US or Canadian benchmark. The placeholders here are three days for a light turn, five for a standard one-bedroom and ten for a heavy one; measure your own.

Can technicians tick it off on a phone?

Yes. Ticks are kept in that browser, per property and unit, until you clear them. Nothing is sent anywhere, so another device starts blank.

Is there a printable make-ready checklist PDF?

Print the page or save it as a PDF: two to three pages with the property, unit, move-out date, timeline, every tick box and an initials and date line per section.